Friday, August 14, 2026 · ACH cutoff 2:00 PM

Weekly Pay Run

Grouped by what is actually blocking the money. Nothing releases until work is verified, the waiver is on file, and the funding source is real.

12 payments
Pay Run Total
All statuses combined
Ready to Release
$187,400
5 payments cleared
Safe to Release Today
$438K
After reserve floor
Blocked by Guardrails
$22,200
7 active holds

Release Capacity

Ready queue measured against today's safe-to-release limit

Ready queue $187,400Safe to release $438,000 · $251K headroom remaining

Ready to Pay — $187,400

5 payments

Ready to Pay

Waiting on Approval — $141,800

3 payments

Waiting on Approval

Waiting on Draw Funding — $61,200

2 payments

Waiting on Draw Funding

On Hold — $22,200

2 payments

On Hold

Payment Guardrails

Automatic holds — a payment cannot be released while one is active

HOLD — Draw Not Funded
Payment sourced to a draw the bank has not wired.
2 active
HOLD — Work Not Verified
PM has not confirmed completed work for the billed amount.
1 active
HOLD — Missing Lien Waiver
Conditional or unconditional waiver not on file.
1 active
HOLD — Change Order Not Approved
Billing exceeds scope without an executed change order.
1 active
HOLD — Over Contract
Cumulative billing exceeds contract or PO value.
1 active
HOLD — Payment Would Breach Cash Reserve
Release would drop cash below the $500K minimum reserve.
0 active
HOLD — Banking Information Changed
Vendor payment instructions changed within 30 days.
1 active

Approval Matrix

Who must sign before a release is possible

Under $10,000Project Manager
$10,000 – $50,000Project Manager + Controller
$50,000 – $150,000PM + Controller + Owner
Over $150,000PM + Controller + Owner + bank draw confirmation

Banking Change Alert

Southshore Electric — payment instructions changed 4 days ago

All Southshore payments held pending a verbal callback to the number on file.
  1. Southshore Electric submitted new ACH routing / account.
    Aug 10, 9:42 AM · vendor portal
  2. All Southshore payments auto-held. Prior instructions retained.
    Aug 10, 9:42 AM · system
  3. Callback attempted to number on file — voicemail left.
    Aug 11, 8:15 AM · Terry Tully
  4. Second verification required before release.
    Pending · Terry Tully

Vendor Compliance

W-9, insurance, license, waivers and banking verification across active vendors

VendorW-9COILicenseLien waiversACHOpen amount
ABC FramingOn fileCurrentCurrentCurrentVerified$68,400
Southshore ElectricOn fileCurrentCurrentCurrentChanged$35,500
Crescent RoofingOn fileExpiredCurrentOutstandingVerified$38,000
Gulf HVAC ServicesOn fileExpiringCurrentCurrentVerified$41,900
Delta Plumbing Co.On fileCurrentCurrentCurrentVerified$42,800
Cypress CabinetsMissingCurrentN/AOutstandingVerified$30,900
Heritage MillworkOn fileCurrentN/ACurrentVerified$52,400

Compliance is checked at release time, not at invoice entry — an expiring COI blocks the payment, not the paperwork.